Which expression correctly defines Average Annual Investment (AAI)?

Prepare for the Heavy Civil Exam 1 with detailed questions and in-depth explanations. Boost your readiness through flashcards and informed practice. Ace your exam with confidence!

Multiple Choice

Which expression correctly defines Average Annual Investment (AAI)?

Explanation:
The expression for Average Annual Investment reflects how much capital is tied up each year when an asset's value decreases linearly from the initial investment P to the salvage value S over n years. Because the first year involves almost the full P and the last year only the salvage value S, the end values are weighted differently across the n years. Working through the linear decrease and averaging over the n years yields a weighted sum whose total per-year average is [P(n+1) + S(n−1)] divided by 2n. This matches the idea that early years contribute more to the average than later ones and gives a consistent result in edge cases (for example, when n = 1, the AAI equals P; if P = S, the AAI equals that common value). The other forms don’t account for the timing weights or misplace the division, so they don’t produce the correct per-year average tied up in capital over the project life.

The expression for Average Annual Investment reflects how much capital is tied up each year when an asset's value decreases linearly from the initial investment P to the salvage value S over n years. Because the first year involves almost the full P and the last year only the salvage value S, the end values are weighted differently across the n years. Working through the linear decrease and averaging over the n years yields a weighted sum whose total per-year average is [P(n+1) + S(n−1)] divided by 2n. This matches the idea that early years contribute more to the average than later ones and gives a consistent result in edge cases (for example, when n = 1, the AAI equals P; if P = S, the AAI equals that common value).

The other forms don’t account for the timing weights or misplace the division, so they don’t produce the correct per-year average tied up in capital over the project life.